PMP (Project Management Professional) Formulas & Calculators

Plug in your numbers and see every result worked out, step by step — then use the reference below to recognise which formula a question is really asking for.

← Back to the full “How to pass PMP (Project Management Professional)” guide

Earned Value calculator

Enter the four EVM inputs to get every variance, index, and forecast — with the worked formula for each.

Cost Variance (CV)

EV − AC = 400 − 500

over budget-100

Schedule Variance (SV)

EV − PV = 400 − 500

behind-100

Cost Performance Index (CPI)

EV ÷ AC = 400 ÷ 500

over budget0.8

Schedule Performance Index (SPI)

EV ÷ PV = 400 ÷ 500

behind0.8

EAC — current performance continues

BAC ÷ CPI = 1,000 ÷ 0.8

1,250

EAC — variance was atypical

AC + (BAC − EV) = 500 + (1,000 − 400)

1,100

EAC — cost & schedule

AC + (BAC − EV) ÷ (CPI × SPI)

1,437.5

Estimate to Complete (ETC)

EAC − AC = 1,250 − 500

750

Variance at Completion (VAC)

BAC − EAC = 1,000 − 1,250

-250

To-Complete Performance Index (TCPI)

(BAC − EV) ÷ (BAC − AC)

1.2

PERT three-point estimate

A beta-weighted estimate that leans on the most-likely value.

Expected estimate (E)

(O + 4M + P) ÷ 6 = (2 + 4×4 + 12) ÷ 6

5

Standard deviation (SD)

(P − O) ÷ 6 = (12 − 2) ÷ 6

1.67

Communication channels

Two-way communication lines among the stakeholders on a project.

Channels

n(n − 1) ÷ 2 = 5 × 4 ÷ 2

10

Formula reference

What each formula means and when to reach for it on exam day.

Frequently asked questions

Does the PMP exam give you the formulas?
No. PMI does not provide a formula sheet, so you need to memorize the earned-value, forecasting, PERT, and communication-channel formulas and recognize when each applies. The Pearson VUE platform does provide a basic on-screen calculator.
Which formulas matter most on the PMP exam?
Earned value management — EV, CV, SV, CPI, and SPI — plus the forecasting formulas (EAC, ETC, VAC, TCPI), PERT three-point estimates, and the n(n − 1) ÷ 2 communication-channels formula. Most quantitative questions reduce to these.